Calendar

M-002

Company weekly

Today, 09:30–10:00· Online· Past

Agenda

  1. Numbers of the week (Lena, 5 min)
  2. Two weeks to release: red, yellow, green (Minh, 10 min)
  3. Support plan for launch week (Sam, 5 min)
  4. Film, first cut (Claire, 5 min)
  5. Questions (5 min)

Notes

Numbers

  • 18,400 paying companies (+96)
  • First answer in support: 98 minutes, best week ever
  • Crash-free sessions: 98.9% (goal 99.5%)
  • Cash: as planned. 2027 budget draft goes to Alex on Friday

Two weeks to release

StatusNext step
Offline mode🟡Conflict screen, then 24-hour test
Tap to pay🟡Android certificate, expected Tuesday
Camera crash🔴Fix in tonight's beta, watch for 48 h
Migration🟡Second dry run on Thursday
Store listing🟢Four languages to go

Support in launch week

Sam asks for two freelancers for two weeks (€3,360). Request is in Approvals. Everyone takes one shift of two hours.

Film

Everybody loved it. Two spots show the old icon.

Decisions

  • Code freeze on Wednesday 17:00.
  • Go/no-go on Thursday 15:00. If the crash fix does not hold, we move by one week and say so the same day.

Follow-up tasks 0/4 done